Taylor Creek / LOPP - Blog #11

The Taylor Creek - Nubbin Slough (TCNS) Basin is directly north of Lake Okeechobee. The watershed covers 120,000 acres of a typically flat landscape with generally poorly drained, coarse textured soils (Spodosols) that have a low phosphorus retention capacity. Water flow from the basin tributaries enters Lake Okeechobee through a flow control structure (S-191).

Lake Okeechobee provides drinking and irrigation water, supports commercial and sport fishing, and is a habitat for many migratory as well as endemic bird species. High phosphorus (P) concentrations in Lake Okeechobee promote eutrophic conditions that impair all water uses.

http://www.water.ncsu.edu/watershedss/info/rcwp/fl1prof.html

Taylor Creek / LOPP - Blog #10

How can I receive the latest information?

 

For additional information on the Lake Okeechobee Critical Restoration Project, please contact Lisa Kreiger, 863-462-5260, e-mail  HYPERLINK "mailto:lhornun@sfwmd.gov" lkreiger@sfwmd.gov. To learn more about the Comprehensive Everglades Restoration Plan, please visit our website at  HYPERLINK "http://www.evergladesplan.org" www.evergladesplan.org.

Taylor Creek / LOPP - Blog #9

Construction of a 170-acre Stormwater Treatment Area for Taylor Creek is complete on a publicly held portion of the Grassy Island Ranch, east of Taylor Creek. The purpose is to divert and treat about 10% of the water flow from Taylor Creek. This is accomplished by allowing the water to flow parallel to the creek for about 1.6 miles through emergent vegetation, before returning to the creek.   This STA started up in October 2006, and was opened for public use in November 2007.

 

The goal for water quality improvement in the Stormwater Treatment Areas is to reduce phosphorus to the maximum extent possible, given the limited area of the Stormwater Treatment Areas to the amount of water available in Taylor Creek and Nubbin Slough. 

Taylor Creek / LOPP - Blog #8

 

Project Description:

 

The project includes two Stormwater Treatment Areas: Nubbin Slough and Taylor Creek, and one isolated wetland/retention pond sites: Byrd Stockyard.

 

Public Lands – Stormwater Treatment Areas 

 

Construction of a 780-acre Stormwater Treatment Area for Nubbin Slough is complete on the former New Palm/Newcomer Dairy. The purpose of this Stormwater Treatment Area is to divert and treat the majority of runoff from Nubbin Slough. This would be accomplished by delivering water from the slough to the east end of the Stormwater Treatment Area. The water would then flow through the treatment wetland and discharge back to the slough.   The Nubbin Slough STA is not currently operational.  .

Taylor Creek / LOPP - Blog #7

Project Purpose:

 

The purpose of this project is to store water runoff and reduce phosphorus on various parcels in the project’s basins. Two approaches are used: construction of Stormwater Treatment Areas on publicly held lands and restoration of isolated wetlands or construction of retention ponds on private lands.  In addition to providing immediate water management and water quality benefits, these Stormwater Treatment Areas will also provide critical information in the design of the larger reservoirs and Stormwater Treatment Areas that are being planned for the Lake Okeechobee Watershed Comprehensive Everglades Restoration Plan Project.

Taylor Creek / LOPP - Blog #5

The Lake Okeechobee Critical Projects were implemented through a partnership between the U.S. Army Corps of Engineers (Corps) and the South Florida Water Management District. The implementation process involves the following phases: planning, engineering and design, construction, operations and maintenance, and monitoring and assessment of project performance.

Taylor Creek / LOPP - Blog #4

In addition to programs designed to diminish the amount of phosphorus runoff into Lake Okeechobee and the amount of exotic plants that are in the lake, LOPP includes a Lake Okeechobee Construction Program, which comprises the Lake Okeechobee Water Retention/Phosphorus Removal Project, a Critical Restoration Project authorized in the federal Water Resources Development Act of 1996. This Critical Project includes the restoration of isolated wetlands and construction of large retention areas, or Stormwater Treatment Areas, which improve the water quality of runoff draining from areas up to several hundred square miles in size. The Lake Okeechobee Construction Program also includes a Comprehensive Everglades Restoration Plan Project – the Lake Okeechobee Watershed Project - which is designed to improve water quality to Lake Okeechobee and downstream receiving waters.

Taylor Creek - Blog #3

The 2000 Florida Legislature established the Lake Okeechobee Protection Program (LOPP), which is designed to address the issues of water quality, hydrology and exotic plant management. An integrated watershed and lake management strategy is being used to improve the condition of Lake Okeechobee. This strategy uses land management practices to reduce phosphorus levels in streams draining land parcels of several hundred acres or less, regional phosphorus control technologies that impact areas ranging in size from several hundred acres to several hundred square miles and in-lake remediation projects. 

Another Taylor Creek Pic!